Project Status, March 27

Activities Completed This Week:

  • Participated in data integration review sessions with UIS.  Confirmed design of education data.
  • Participated in MEC’s call. 
  • Reviewed community field mapping requirements.Started build of custom  objects.Continued build of Exacttarget email personalization options.
  • Reviewed ExactTarget blue print. 

 

Activities Planned for Next Week:

  • Continue ExactTarget build
  • Salesforce build and configuration:  Custom objects and fields
  • Build data mapping document (mapping from sources systems, MDM to Salesforce)
  • Begin to build configuration workbook

 