We have the following updates to share about FIN 9.2 this week.

Making progress

  • We completed April month-end close according to the normal schedule – that is, we closed at the usual third business day. The HCM team has corrected April payroll encumbrance information – with the exception of some additional pay – so your April m-Fin reports are now pulling updated data.
  • Letter of credit draws are now complete through March.
  • We’ve finalized plans to catch up on system invoicing through March. We expect to complete this by June 1.

Need to improve

  • We’re developing a process to clean up your approval worklists by removing any journals that have already been approved.
  • We’re finalizing a Query that will show details of Treasury journal transactions.

Issues Lists

Remember that our issues lists are updated regularly on the OUC website [3].

Continue to let us know what you notice

Contact FinProHelp@cu.edu [4].

Display Title: 
FIN 9.2 Recap - May 6
Send email when Published: 
No

Source URL:https://www.cu.edu/blog/ouc-news/fin-92-recap-may-6

Links
[1] https://www.cu.edu/blog/ouc-news/fin-92-recap-may-6 [2] https://www.cu.edu/blog/ouc-news/author/752 [3] https://www.cu.edu/controller/elevate [4] mailto:FinProHelp@cu.edu