Activities Completed This Week:
  • Conducted vendor demonstrations for event management tool (Linvio, Eventbrite, Cvent).
  • Continued work on Community build.
  • Hand off of ExactTarget blue print to ACF. In review (this document is ET’s design document based on our requirements. Will be delivered to CU week of 3/23.
  • Conducted in depth data integration meeting (Dennis, Alanna, Molly, Lisa, Sharon).
  • Created email personalization template (to be delivered to CU week of 3/23).
  • Created Community custom setting document.
  • Configured ExactTarget users.
Activities Planned for Next Week:
  • Continue ExactTarget build
  • Salesforce build and configuration: Custom objects and fields
  • Build data mapping document (mapping from sources systems, MDM to Salesforce)
  • Begin to build configuration workbook
  • Deliver updated project timeline
  • Deliver ExactTarget blueprint
  • Participate in MEC’s meeting