Activities Completed This Week:

  • Design Document completed
  • Planning and preparation for onsite next week
  • Review of ExactTarget data extension solution
  • Community design review
  • Schedule of event management tool demos

Activities Planned for Next Week:

  • Submit design document
  • Onsite meetings scheduled
    • Review and finalize data model
    • Review and finalize remaining project schedule
    • Review and finalize data integration requirements and transformation needs
    • Review security
  • Begin Salesforce Build