Activities Completed This Week:

  • Participated in data integration meetings. Determine mapping and layout of education object data.
  • Participated in calls with Linvio and Salesforce to determine PCI Compliance and next steps (4/1).
  • Design online community to trigger to automatically keep constituent contact and use accounts in sync.
  • Designed eComm security profiles for users.

Activities Planned for Next Week:

  • Continue ExactTarget build.
  • Receive hand off from Dev for the online community custom settings (allow ACF to configure community to eComm’s specs).
  • Salesforce build and configuration: Build Education and interest objects.
  • Follow up with linvio/event management tools.