Activities Completed This Week:
- Participated in data integration meetings. Determine mapping and layout of education object data.
- Participated in calls with Linvio and Salesforce to determine PCI Compliance and next steps (4/1).
- Design online community to trigger to automatically keep constituent contact and use accounts in sync.
- Designed eComm security profiles for users.
Activities Planned for Next Week:
- Continue ExactTarget build.
- Receive hand off from Dev for the online community custom settings (allow ACF to configure community to eComm’s specs).
- Salesforce build and configuration: Build Education and interest objects.
- Follow up with linvio/event management tools.